Pile driving began October 1, 2014 at 10:00am.
Foundation was poured December 8, 2014 Framing began over the christmas holidays. Second floor concrete poured January 20, 2015. Third floor concrete slab poured, February 10, 2015. The structure of our building is complete! The roof is being finished, as weather permits, windows are going in and drywall is going up inside the building! April 14, 2015 We can finally say we are covering up the weatherproof pink! May 11, 2015 We are so pleased to announce the outer part of the center is almost fully painted! June 16th, 2015